The 90-day settlement period for the fill dirt that was placed on the embankments is set to end on February 8, 2010. As this milestone approaches, Powell Constructors will resume work beginning next week. The construction scheduled for the period of February 8th through February 12th, 2010 will include night work and ramp closures on Monday and Tuesday. The updated work schedule includes the following:
NIGHT WORK
MONDAY, FEBRUARY 8TH and TUESDAY, FEBRUARY 9TH- Beginning at approximately 10:00 PM the contractor will begin mobilizing and setting up the pile driving equipment within the center divider on the U.S. 101. Work is to conclude no later than 6:00 AM Tuesday and Wednesday mornings.
DAY WORK
MONDAY, FEBRUARY 8th THROUGH FRIDAY, FEBRUARY 12TH - Work will begin on Monday at approximately 9:00AM on the northwest embankment and culvert area between the northbound on-ramp and Canwood Street. The work will include excavating the embankment and filling the culvert area for the bridge widening. Ramp closures are scheduled both Monday and Tuesday from 9:00AM-Noon to complete this work.
**PLEASE NOTE ONLY THE NORTHBOUND ON-RAMP IS SCHEDULED TO BE CLOSED DURING FROM 9:00 AM- NOON. ALL OTHER RAMPS ARE SCHEDULED TO REMAIN OPEN.
WEDNESDAY, FEBRUARY 10th THROUGH FRIDAY, FEBRUARY 12TH - Workfor the center divider bents is scheduled to begin Wednesday along the U.S. 101 freeway. A bent is a column that supports each end of a bridge span. The force of the equipment drive piling may cause heavy vibrations. Please use caution when approaching the area.
All businesses within the proximity of the interchange will be open and fully accessible during construction. Thank you for your continued patience.
PLEASE NOTE: Kanan and Lindero Canyon Roads can be used as alternate exits for those wishing to avoid construction traffic. Please observe all traffic control and construction zone speed limits. For more information, please email Public Works Project Manager Kelly Fisher at kfisher@ci.agoura-hills.ca.us